Connected Cully Sidewalk Infill: NE Killingsworth Street and NE Prescott Street

Transportation
Under Construction
The Portland Bureau of Transportation (PBOT) will construct missing sidewalk on NE Killingsworth Street and NE Prescott Street between NE 42nd Avenue and NE Cully Boulevard. Sidewalk construction also includes rebuilding corner ramps and driveway connections, where needed.
Construction starts February 2021
On this Page

What's happening now?

Design engineering and right-of-way are complete, and the state and federal governments have authorized the construction phase. The project was advertised for bids on October 8, 2020. Construction is scheduled to start in February 2021 and last until November 2021.