82nd Avenue: Klickitat to Lambert Crossings

Transportation
Under Construction
As part of this project, the Portland Bureau of Transportation (PBOT) will make critical pedestrian crossing improvements to 82nd Avenue at seven intersections between NE Klickitat and SE Lambert streets.
Pedestrians cross a four-lane street with landscaped, tree-lined median islands in the center lane. Drivers wait at a red light while pedestrians cross.
Construction 2023-2026
On this Page

What's happening now?

November 1, 2024 Update

A construction worker in a white bucket truck installs a signal head on a new signal pole

Contractors with PBOT install signal heads on a new mast arm at NE 82nd Avenue and Schuyler Street. 

Upcoming work in the next two weeks includes: 

  • NE Klickitat– Tree planting and electrical work
  • NE Schuyler– Concrete median island construction
  • SE Clinton No work next 2 weeks
  • SE Schiller– Concrete median island construction

The traveling public can expect to see lane closures and side street closures at intersections with construction activity as part of this work.

No construction activity will take place from November 23 to December 1 due to the Holiday Moratorium. 

September 6, 2024 Update

A construction worker in a bucket installs a traffic signal head on a silver mast arm. The signal sits atop a newly constructed sidewalk with orange construction fencing and cars in a parking lot in the background.
A construction worker in a bucket installs a traffic signal head at SE 82nd Avenue and Schiller Street. In August, contractors with PBOT installed traffic signal equipment on NE/SE 82nd Avenue at the intersections of Schuyler, Clinton and Schiller streets. These intersections are three of six new pedestrian crossings coming to 82nd Avenue in 2024.

Current construction activities: 

  • NE Schuyler– Utility relocations and corner ramp reconstruction

The traveling public can expect to see lane closures and side street closures at intersections with construction activity as part of this work.

July 11, 2024 Update

Sidewalk and sidewalk trees next to a roadway partially dug up with orange construction fencing around it
Roadway excavation at SE 82nd Avenue at Clinton Street. As part of the 82nd Avenue Crossings Project, PBOT will install six signalized pedestrian crossings with median islands along 82nd Avenue. PBOT will upgrade crossings to new pedestrian half-signals, full signals, or pedestrian beacons. In addition to the signal improvements, PBOT will install accessible curb ramps, high-visibility crosswalks, concrete median islands.

In the coming week, contractors with PBOT are continuing roadway excavation, regrading and repaving at SE 82nd Avenue at Clinton Street. In addition, contractors will begin saw cutting pavement on SE 82nd Avenue south of Schiller, where a new median island will be installed. Later this fall after temperatures drop, trees and other vegetation will be planted in the median island. 

June 28, 2024 Update

A truck and trailer drive on smooth new pavement across an intersection with new curb ramps and construction fencing
Smooth new pavement and curb ramps on SE Clinton Street looking east across 82nd Avenue.  As part of the 82nd Avenue Crossings Project, PBOT will install six signalized pedestrian crossings with median islands along 82nd Avenue.

In the coming weeks, contractors with PBOT are continuing curb ramp construction and paving. No work will take place over the upcoming holiday weekend, July 4 – 7.  

This summer, contractors will begin installing signal poles and constructing median islands. Later this fall after temperatures drop, trees will be planted in these median islands. We anticipate construction will be complete in spring 2025.    

May 30, 2024 Update

Construction continues, with signal poles and median islands coming this summer to improve safety

Pedestrians cross a four-lane street with landscaped, tree-lined median islands in the center lane. Drivers wait at a red light while pedestrians cross.
As part of the 82nd Avenue Crossings Project, PBOT will install four signalized pedestrian crossings with median islands along 82nd Avenue, similar to this example rendering. As part of the project, PBOT will upgrade crossings to new pedestrian half-signals or full signals. In addition to the signal improvements, PBOT will install accessible curb ramps, high-visibility crosswalks, concrete median islands. Within the intersections, medians will feature a red stamped brick pattern. Trees are set back from the intersection to maintain visibility and allow for emergency vehicle movements.

In the coming weeks, contractors with PBOT are continuing curb ramp construction and excavation for electrical conduit and signal foundations.  

As soon as July, contractors will begin installing signal poles and constructing median islands. Later this fall after temperatures drop, trees will be planted in these median islands. We anticipate construction will be complete in spring 2025.  

In a 10-year period (2012-2021), more than 90% of traffic deaths on 82nd Avenue were pedestrians or bicyclists, or people in cars turning left at locations without signals.  Safe crossings and median islands are two of the most effective measures to reduce or eliminate those types of crashes.  

Overview of updated traffic operations  

  • NE/SE 82nd Avenue at the intersections of NE Klickitat, NE Schuyler, and SE Clinton streets:   

    • People driving will no longer be able to turn left or drive across 82nd Avenue at these intersections.  

    • People driving north and south on 82nd Avenue will be able to turn right onto side streets, turn right into and out of driveways, or continue straight on 82nd. 

    • People driving east and west on side streets will be able to turn right onto 82nd Avenue.  

  • SE 82nd Avenue at the intersection of Schiller Street:   

    • People driving south will no longer be able to turn left into one driveway south the intersection.  

    • All other turning movements permitted today will continue to be permitted.  

May 17, 2024 Update

Construction workers in orange vests and hard hats finish ADA curb ramps and sidewalk. Wooden forms and stakes hold concrete in place.
Construction crews finish concrete for new ADA curb ramps and sidewalk at SE 82nd Avenue at SE Schiller Street.

In the coming weeks, contractors with PBOT will continue curb ramp construction and excavation for electrical conduit and signal foundations. Contractors are currently working at 82nd Avenue, at the intersections of 82nd Avenue at NE Klickitat and Schuyler streets; and SE Clinton and Schiller streets.

Traffic impacts: 

  • Temporary pedestrian walkways – physical barriers will be in place to direct pedestrians around the work zone during construction.

  • Temporary lane closures – one travel lane on 82nd Avenue will be closed near the work zones. 

  • During the Memorial Day Holiday weekend, contractors will complete construction activity by noon Friday, May 24. No work is planned over the weekend, and no work is planned for Memorial Day, Monday, May 27.

April 10, 2024 Update

Initial work is underway to construct six new pedestrian crossings on 82nd Avenue. This month, contractors with PBOT will continue to construct inlets and ADA corner ramps on SE 82nd Avenue at the intersections of SE Schiller Street and at SE Clinton Street. 

March 21, 2024 Update

Initial work is underway to construct six new pedestrian crossings on 82nd Avenue. In the coming weeks, contractors with PBOT will construct inlets and ADA corner ramps. This work will take place at SE 82nd Avenue at the intersections of SE Schiller Street and at SE Clinton Street. 

Traffic impacts: 

  • Temporary pedestrian walkways – physical barriers will be in place to direct pedestrians around the work zone during construction. 

  • Temporary lane closures - one travel lane on 82nd Avenue will be closed near the work zones. 

  • Road closures of side streets – SE Schiller and SE Clinton streets may be closed to residential vehicles for up to two weeks while concrete cures and pavement is restored.

Design is nearing completion on three additional crossings of SE 82nd Avenue at the intersections of Ramona, Tolman and Lambert. 

Learn more about the designs below.

February 28, 2024 Update

Planned construction activities for the next three weeks include underground electrical conduit installation. Work will take place at SE 82nd Avenue at the intersections of Clinton and Schiller. 

Design continues on three additional crossings of SE 82nd Avenue at the intersections of Ramona, Tolman and Lambert. Learn more about the designs below.

February 1, 2024 Update

Planned construction activities for this month include storm installation, sump testing, and underground electrical conduit. Work will take place at 82nd Avenue at the intersections of Klickitat, Schuyler, Clinton, and Schiller. 

Design continues on three additional crossings of SE 82nd Avenue at the intersections of Ramona, Tolman and Lambert. Learn more about the designs below.

January 3, 2024 Update

Planned construction activities for this week include tree removal at 82nd Avenue at the intersections of Clinton, Schuyler, Schiller and Beech. Trees near the existing curb ramps at these intersections are being removed in order to construct new ADA-compliant curb ramps. 

The project will be mitigating the tree removals and replanting where feasible in accordance with Urban Forestry's rules. 

Design continues on three additional crossings of SE 82nd Avenue at the intersections of Ramona, Tolman and Lambert. Learn more about the designs below.

December 27, 2023 Update

No construction planned until January 2, 2024. Planned construction activities for the first half of January include underground and sewer work on NE/SE 82nd Avenue at the intersection of SE Schiller. In addition, SUMP testing will be conducted at:

  • NE Klickitat
  • NE Schuyler
  • SE Clinton 
  • SE Schiller

Design continues on three additional crossings of SE 82nd Avenue at the intersections of Ramona, Tolman and Lambert. Learn more about the designs below.

December 2023 Update

An excavator drops debris into a truckbed behind the NE Klickitat St and NE 82nd Ave street signs.
Underground and sewer construction activity began at NE 82nd and Klickitat in November 2023.

Planned construction activities this month include underground and sewer work on NE/SE 82nd Avenue at the intersections of:

  • NE Klickitat
  • NE Schuyler
  • SE Clinton 

November 2023 Update

Contractors with PBOT will begin construction on Monday, November 13. Construction activity will take place on 82nd Avenue at NE Beech, Klickitat, and Schuyler streets; and SE Clinton, Ash, and Schiller streets. 

The new crossings are being delivered together with street lighting improvements on 82nd Avenue from NE Lombard to SE Clatsop streets and on NE Halsey Street from NE 112th to 162nd avenuesStreet lighting improvements will begin in 2024.

Construction on the pedestrian crossings and street light improvements is expected to last up to 18 months.

Work will be conducted in multiple phases with periods of inactivity between each phase ranging from a few weeks to several months. Construction activities in the first weeks of the project will include sewer and underground improvements. After underground improvements are complete, the contractor will begin to construct curb ramps at the six intersections.

Work hours

Typical work hours will be 7 a.m. to 5 p.m., Monday through Friday. There may be occasional evening or weekend work.  

What to expect during construction

  • Construction creates noise, vibration and dust.
  • Construction activities may impact neighborhood activity and normal use of driveways or business entrances. The contractor will provide advanced notification of impacts to adjacent property owners and residents.
  • Expect traffic delays in and near the work area. Please observe traffic control signs and follow the directions of flaggers.
  • On‐street parking may be restricted in and near the work zones to create a safe work environment and to stage equipment and materials.
  • Some equipment and materials may be stored in the public right-of-way overnight.

Traffic impacts

  • The traveling public should expect lane closures and delays on 82nd Avenue and side streets near the work zones.
  • We ask the public to travel slowly and cautiously in the work zones, observe all directions by flaggers and use alternate routes if possible.
  • People riding transit can visit trimet.org/#alerts/ for the latest service impacts. 
  • This work is weather-dependent, and the schedule may change.
  • Thank you for your cooperation and patience while we complete this work.

July 2023 Update

Klickitat, Schuyler, Clinton, and Schiller crossings: The PBOT project team and contractor are preparing for construction. Minor construction activity related to utility work is anticipated in summer 2023. Construction of the crossings are anticipated to begin in fall or winter 2023. The project team will share a more detailed construction schedule this fall. 

Ramona, Tolman, and Lambert crossings: Designs are advancing to 60%. 

December 2022 Update

The project team has finalized designs of Klickitat, Schuyler, Clinton, and Schiller crossings. The project will go to bid in winter 2023 and construction will begin in summer 2023.

The project team is preparing preliminary designs for the Ramona, Tolman, and Lambert crossings. 

Project overview 

PBOT will be adding features proven to reduce fatal and serious injuries occurring in traffic crashes along 82nd Avenue. In the most recent 5-year period, all 9 fatal crashes and more than half of the 59 serious injury crashes on 82nd Avenue in Portland were either pedestrians or cars turning at locations without signals.

Safe pedestrian crossings and medians are two of the most effective measures to reduce or eliminate these types of crashes. The new pedestrian crossings with tree-lined median islands will provide safe and comfortable places for people to cross 82nd, will reduce the risk of turning crashes, and will help define 82nd Avenue as street serving the community, not just a highway.

As part of this project, the Portland Bureau of Transportation (PBOT) will make critical pedestrian safety improvements to 82nd Avenue between NE Klickitat and SE Lambert Street. 

The current crossings will be upgraded to new pedestrian half signals, full signals or pedestrian beacons. 

In addition to the signal improvements, PBOT will install accessible curb ramps and high-visibility crosswalks all locations and concrete median islands. Additional details are below. 

Crossings in construction in 2023 - 2025

NE Klickitat Street

At NE 82nd and Klickitat Street, PBOT will install a pedestrian half signal, a protected concrete median refuge, curb ramps and new marked crosswalks. 

On-street Parking impacts: There is no permanent parking removal at NE Klickitat as part of this project. 

Overview of updated traffic operations 

With the new median, people driving will no longer be able to turn left or travel across 82nd Avenue at NE Klickitat. 

  • People driving north on 82nd Avenue will be able to: Turn right onto Klickitat, turn right into driveways, or continue straight on 82nd Avenue 
  • People driving south on 82nd Avenue will be able to: Turn right onto Klickitat, turn right into driveways, or continue straight on 82nd Avenue 
  • People driving east on Klickitat will be able to: Turn right onto 82nd Avenue 
  • People driving west on Klickitat will be able to: Turn right onto 82nd Avenue 
NE Schuyler Street

At NE 82nd and Schuyler Street, PBOT will install a signal with pedestrian and bicycle priority, a protected concrete median refuge, curb ramps, new marked crosswalks and new green bike boxes.

On-street Parking impacts:

  • East of 82nd Avenue: On the north side of NE Schuyler, approximately two to three spaces of on-street parking on NE Schuyler will be removed to install a new green bike box.
  • West of 82nd Avenue: On the south side of NE Schuyler, approximately two to three spaces of on-street parking will be removed to install a new green bike box.

Updated traffic operations 

After construction is complete, people driving will no longer be able to turn left or travel across 82nd Avenue at NE Schuyler. 

  • People driving north on 82nd Avenue will be able to: Turn right at Schuyler Street, turn right into and out of driveways, or continue straight on 82nd 
  • People driving south on 82nd Avenue will be able to: Turn right at Schuyler Street, turn right into and out of driveways, or continue straight on 82nd 
  • People driving east on Schuyler will be able to: Turn right onto 82nd Avenue 
  • People driving west on Schuyler will be able to: Turn right onto 82nd Avenue 

SE Clinton Street

At SE 82nd and Clinton Street, PBOT will install a pedestrian half signal, a protected concrete median refuge, curb ramps and new marked crosswalks. 

On-street Parking Impacts: There is no permanent parking removal at SE Clinton as part of this project.

Updated traffic operations 

After construction is complete, people driving will no longer be able to turn left or travel across 82nd Avenue at the SE Clinton. 

  • People driving north on 82nd Avenue will be able to: Turn right at Clinton Street, turn right into and out of driveways, or continue straight on 82nd 
  • People driving south on 82nd Avenue will be able to: Turn right at Clinton Street, turn right into and out of driveways, or continue straight on 82nd 
  • People driving east on Clinton Street will be able to: Turn right onto 82nd Avenue 
  • People driving west on Clinton Street will be able to: Turn right onto 82nd Avenue 
SE Schiller Street

At SE 82nd and Schiller Street, PBOT will install a new traffic signal, a concrete median, curb ramps and new marked crosswalks. 

On-street Parking Impacts: For improved traffic and signal operations, approximately five to six parking spaces will be removed on the north side of SE Schiller, east of 82nd Avenue. 

Updated traffic operations 

After construction is complete, people driving will no longer be able to turn left into one driveway south the intersection. 

  • People driving north on 82nd Avenue will be able to: Turn right at Schiller Street, turn right into and out of driveways, or continue straight on 82nd
  • People driving south on 82nd Avenue will be able to: Turn left at Schiller Street, turn right into and out of 
  • driveways, or continue straight on 82nd
  • People driving west on Schiller Street will be able to: Turn left or right onto 82nd Avenue

Crossings in design (construction in 2025 - 2026)

SE Ramona Street

At 82nd and Ramona, PBOT will install a signalized pedestrian crossing, a protected concrete median refuge island, curb ramps and new marked crosswalks. PBOT will also plant trees and other vegetation in the medians where feasible.

On-street Parking Impacts: There is no permanent parking removal at SE Ramona as part of this project.

Updated traffic operations 

With the new median, people driving will no longer be able to turn left where Ramona intersects 82nd Avenue. 

  • People driving north on 82nd Avenue will be able to: Turn right at Ramona, turn right into and out of driveways near the intersection, or continue straight on 82nd
  • People driving south on 82nd Avenue will be able to: Turn right at Ramona, turn right into and out of driveways near the intersection, or continue straight on 82nd
  • People driving east on Ramona will be able to: Turn right onto 82nd Avenue
  • People driving west on Ramona will be able to: Turn right onto 82nd Avenue
  • People driving east on Knight will be able to: Turn left or right at 82nd Avenue
SE Tolman Street

At SE 82nd and Tolman, PBOT will install a signalized pedestrian and bicycle crossing, a protected concrete median refuge island, curb ramps and new marked crosswalks. This crossing also supports SE Tolman as a future neighborhood greenway. In addition, PBOT will also plant trees and other vegetation in medians where feasible.

Updated traffic operations 

With the new median, people driving will no longer be able to turn left or travel across 82nd Avenue at the intersection. 

  • People driving north on 82nd Avenue will be able to: Turn right at Tolman, turn right into and out of driveways near the intersection, and continue straight on 82nd
  • People driving south on 82nd Avenue will be able to: Turn right at Tolman, turn right into and out of driveways near the intersection, and continue straight on 82nd
  • People driving east on Tolman will be able to: Turn right onto 82nd Avenu
  • People driving west on Tolman will be able to: Turn right onto 82nd Avenue
SE Lambert Street

At SE 82nd and Lambert Street, PBOT will install a new traffic signal, concrete traffic separators, curb ramps and new marked crosswalks.

Updated traffic operations 

With the new traffic signal, pedestrians and people biking will have a safe place to cross 82nd Avenue. People driving will also benefit from improved safety crossing and turning at 82nd and Lambert. To further protect left turning vehicles from on-coming traffic, a concrete traffic separator will be installed. We understand that this traffic separator may affect access to your business. If you have specific access concerns, please contact us to discuss.

  • People driving north on 82nd Avenue will be able to: Turn left or right at Lambert, turn right into driveways near the intersection, or continue straight on 82nd Avenue
  • People driving south on 82nd Avenue will be able to: Turn left or right at Lambert, turn right into driveways near the intersection, or continue straight on 82nd Avenue
  • People driving east on Lambert will be able to: Turn left or right at 82nd Avenue, turn left or right into driveways near the intersection, or continue straight on 82nd Avenue
  • People driving west on Lambert will be able to: Turn left or right at 82nd Avenue, turn left or right into driveways near the intersection, or continue straight on 82nd Avenue

Sign up for Building a Better 82nd Email Updates

Sign up for email updates


Project timeline

Construction of Klickitat, Schuyler, Clinton, and Schiller crossings began in 2023. Construction is expected to last through spring 2025.

Construction of Ramona, Tolman, and Lambert crossings is expected to begin in spring 2025. Construction is expected to last through the end of 2026.

Project funding

$4.7M from American Rescue Plan Act (ARPA) funds.

Public involvement 

PBOT faces a tight timeline to deliver critical fixes on 82nd Avenue. 

To meet construction deadlines, PBOT will rely on insights from the extensive community engagement the bureau and other agencies conducted over the past 10 years, including:  

Through the ODOT-led planning process (2018), PBOT identified priority enhanced crossing locations on 82nd Avenue. These were vetted with the community through the planning process and included in the ODOT 82nd Avenue of Roses Implementation Plan. The crossing location recommendations included Ash and Beech intersections.

The City conducted interviews with property owners, business owners, and community members, as well as market research to better understand barriers to redevelopment.

 Learn more about opportunities for public engagement

Map