2022 Traffic Signals Superbundle

Transportation
Under Construction
New traffic signals at: SW Naito Parkway & SW Whitaker St, SE 52nd Ave & SE Woodstock St, NE MLK Blvd & NE Going St, E Burnside St & SE 16th Ave, SE Washington St & SE 86th Ave, SE 148th Ave & SE Main St, NE Glisan St & NE 113th Ave, plus street lighting on NE Glisan St from NE 82nd-162nd
traffic signal under construction
Construction begins spring 2023
On this Page

Construction Schedule

SE Woodstock Blvd & SE 52nd Ave:Spring – Fall 2023 (tentative)
  • Construction will begin in April, removing structures and/or obstructions necessary for construction to safely begin.
  • Intersection paving will begin in late May or June.
  • Pouring concrete and installing stormwater management features (inlets) in June.
  • Temporary street striping will occur mid-summer.
  • Installation of the traffic signal pole and equipment should occur in July and August, depending on pole lead times.
  • Permanent street striping and traffic sign installations in late summer or early fall.
  • Street trees will be planted as our final phase of this intersection in fall. 
E Burnside St. & NE 16th Ave:Spring – Fall/Winter 2023 (tentative)
  • Construction will begin in April, removing structures and/or obstructions necessary for construction to safely begin.
  • Sidewalk and curb concrete will be poured in late summer or fall 2023.
  • Temporary street striping will occur as weather permits.
  • Installation of the traffic signal pole and equipment should occur throughout the summer/fall, depending on pole lead times.
  • Landscape work will begin late fall or winter 2023 as our final phase of this intersection.
SW Naito Pkwy & SW Whitaker St: Summer 2023 – Winter 2024 (tentative)
  • Construction crew will arrive in late summer 2023, removing anything necessary for construction to safely begin.
  • Installation of stormwater management features (inlets) and sidewalk/curb concrete to be poured in fall 2023.
  • Temporary street striping will occur late fall.
  • Installation of the traffic signal pole and equipment will occur late October into November.
  • Permanent striping is planned for spring 2024 when the weather dries out, but could occur earlier if conditions allow.
NE MLK Jr. & NE Going St:Summer 2023 – Winter 2024 (tentative)
  • Construction crew will arrive in early summer 2023, removing anything necessary for construction to safely begin.
  • Temporary street striping will occur late summer.
  • Sidewalk and curb concrete will be poured in fall.
  • Installation of the traffic signal pole and equipment will occur throughout late summer/fall.
  • Permanent street striping and traffic sign installations will also occur fall.
  • Street trees will be planted as our final phase of this intersection in late fall.
NE Glisan St. & NE 113th Ave:Winter 2023 – Summer 2024 (tentative)
  • Construction crew will arrive in late 2023 or early 2024, removing anything necessary for construction to safely begin.
  • Sidewalk and curb concrete will be poured spring 2024, along with temporary street striping.
  • Installation of the traffic signal pole and equipment should occur spring 2024.
  • Permanent street striping will occur in early summer 2024. 
  • Landscape work will begin spring/summer 2024 as our final phase of this intersection.
SE Main St. & SE 148th Ave:Fall 2023 – Summer 2024 (tentative)
  • Construction crew will arrive in fall 2023, removing anything necessary for construction to safely begin.
  • Sidewalk and curb concrete will be poured early 2024.
  • Temporary street striping will occur mid-winter 2024.
  • Installation of the traffic signal pole and equipment should occur mid-winter as well.
  • Traffic sign installations will occur late winter.
  • Permanent street striping will occur in spring or summer 2024 as conditions permit. 
  • Landscape work and street tree plantings will occur end of winter or early spring.
SE Washington & SE 86th Ave: Spring– Summer 2024 (tentative)
  • Construction crew will arrive in spring 2024, removing anything necessary for construction to safely begin.
  • Sidewalk and curb concrete will be poured late spring 2024.
  • Installation of the traffic signal pole and equipment should occur spring or summer 2024.
  • Permanent street striping will occur spring 2024, along with landscaping.

Project Scope & Background

The Portland Bureau of Transportation's (PBOT) 2022 Traffic Signals Superbundle project will construct seven new signalized crossings:

  • SW Naito Parkway & SW Whitaker Street - Rectangular rapid flashing beacon
  • SE 52nd Avenue & SE Woodstock Street - Full traffic signal replacement
  • NE MLK Boulevard & NE Going Street - Half signal (stops traffic on MLK to aid crossing)
  • E Burnside Street & SE 16th Avenue - Rectangular rapid flashing beacon on mast arms above street
  • SE Washington Street & SE 86th Avenue - Rectangular rapid flashing beacon mounted on sidewalk
  • SE 148th Avenue & SE Main Street - Pedestrian hybrid beacon (stops traffic on 148th to aid crossing)
  • NE Glisan Street & NE 113th Avenue - Pedestrian hybrid beacon (stops traffic on Glisan to aid crossing)
  • Plus street lighting on NE Glisan Street from NE 82nd to NE 162nd Streets

PBOT will also construct related ADA and stormwater improvements as part of the project. 

Most of the traffic signals in the 2022 Signals Superbundle project emerged from the 2017 Safe Routes to Schools public involvement effort and will help children cross busy streets to get to school. Each traffic signal has its own dedicated funding source, including from Fixing Our Streets, System Development Charges (SDCs), general fund, and Cannabis Tax.

Map

Contact

David Backes

Capital Project Manager, PBOT

News and notices

Updated