Throughout the year, Portland Bureau of Transportation (PBOT) crews and contractors handle all types of basic road maintenance projects to preserve pavement conditions, so it lasts longer. These are projects bigger than a single pothole or utility cut, and not part of any capital improvement project. 

For upcoming projects, visit:

Basic road maintenance schedule

All projects listed below were completed during fiscal year 2025-2026 (July 1, 2025 – June 30, 2026). Work listed by quadrant, then alphabetically by street segment.


North Portland

  • N Argyle Way (2500 block). Paving work to remove cavity in the street. Completed July 9, 2025.
  • N Baltimore Avenue from Bradford to Lombard streets. Crack seal preventive maintenance of road surface. Completed July 24, 2025.
  • N Blandena Street from Michigan to Vancouver avenues. Crack seal preventive maintenance of road surface. Completed July 22, 2025.
  • N Gilbert Avenue (7500 block). Install speed bumps. Completed July 22 to Aug. 5, 2025.
  • N Lombard Street (6900 block). Street grind and repave to ODOT standards for Water Bureau. Completed Aug. 21, 2025.
  • N Smith Street (8100 block). Remove tree roots to improve drainage. Completed Sept. 25, 2025.
  • N St. Louis Avenue (9100 block). Paving work to remove cavity in the street. Completed Nov 6, 2025.
  • N Tioga Avenue (7500 block). Paving work to remove cavity in the street. Completed Nov 6, 2025.
  • N Woolsey Avenue (7500 block). Install speed bumps. Completed Aug. 11-12, 2025.

Northeast Portland

  • NE 11th Avenue (5000 block). Paving work to eliminate potholes. Completed July 17, 2025.
  • NE 17th Avenue (2600 block). Base Repair- Paving work to remove cavity in the street. Completed April 6-10, 2026
  • NE 21st Avenue (700 block). Paving work to eliminate potholes. Completed July 1 - 10, 2025.
  • NE 26th Avenue (Broadway to Knott) Street grind and repave. Completed Sept 22-Oct 4, 2025.
  • NE 33rd Avenue (2700 block). Paving to repair ADA curb ramp. Completed Nov 18, 2025.
  • NE 33rd Avenue (4500 block). Paving to repair ADA curb ramp. Completed Nov 19, 2025.
  • NE 33rd Avenue (1900 block). Paving to repair ADA curb ramp. Completed Nov 24, 2025.
  • NE 38th Avenue (3300 block). Install speed bumps. Completed Aug. 27, 2025.
  • NE 42nd Avenue (4500 block). Paving work to eliminate potholes. Completed Oct 8, 2025.
  • NE 44th Avenue (800 block). Paving work to remove cavity in the street. Completed Aug.27, 2025.
  • NE 45th Avenue (2800 block). Paving work to remove cavity in the street. Completed Nov 6, 2025.
  • NE 48th Avenue (500 block). Regrade ditch line. Completed July 15, 2025.
  • NE 87th Avenue (500 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Sept 29-30, 2025.
  • NE 87th Avenue (1100 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 22-24, 2025.
  • NE 87th Avenue (Glisan to Hassalo streets). Street grind and repave. Completed April 2026.
  • NE 105th Avenue (4800 block). Paving work to remove cavity in the street. Completed July 16, 2025.
  • NE 148th Avenue (2500 block). Paving work to remove cavity in the street. Completed July 15, 2025.
  • NE Alderwood Road from NE 82nd Avenue to NE 105th Avenue. Crack seal preventive maintenance of road surface. Completed July 25, 2025.
  • NE Broadway (22nd Avenue to 11th Avenue) Street grind and repave. Completed July 21-Aug 13, 2025.
  • NE Broadway (1300 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed July 1-2, 2025.
  • NE Broadway (1500 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed July 10-17, 2025.
  • NE Broadway (2100 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed July 7-10, 2025.
  • NE Dekum Street from NE 22nd Avenue to NE Clarmont Street. Crack seal preventive maintenance of road surface. Completed July 24-25, 2025.
  • NE Euclid Street (4700 block). Paving work to remove cavity in the street. Completed Aug. 14, 2025.
  • NE Grand Avenue (800 block). Paving work to remove cavity in the street. Completed Aug. 1, 2025.
  • NE Hancock Street (1700 block). Paving work to eliminate potholes. Completed July 23, 2025.
  • NE Hassalo Street (4000 block). Paving work to remove cavity in the street. Completed Aug 28-Sept 8, 2025.
  • NE Hassalo Street (4000 block). Paving work to remove cavity in the street. Completed Oct 9, 2025.
  • NE Martin Luther King Jr Boulevard (Holladay to Burnside streets). Street grind and repave. Sept 2-25, 2025.
  • NE Martin Luther King Jr Boulevard (Weidler to Holladay streets). Street grind and repave. Aug 25-28, 2025.
  • NE Marx Street (112th to 115th avenues). Paving work to backfill gaps after separate ADA curb ramp work. Completed April 7-10, 2026
  • NE Prescott Street from NE 105th Avenue to NE 121st Avenue. Crack seal preventive maintenance of road surface. Completed July 28-29, 2025.
  • NE Russell Street (15900 block). Paving work to eliminate potholes. Completed Sept 23, 2025.
  • NE Sacramento Street (13200 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 1-4, 2025.
  • NE Sacramento Street (13300 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 5-6, 2025.
  • NE Sacramento Street (13800 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 10-20, 2025.
  • NE Sacramento Street (13900 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 13-21, 2025.
  • NE Sacramento Street (14200 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 17-18, 2025.
  • NE Sacramento Street (14300 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 19-20, 2025.
  • NE Sacramento Street (14200 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 24-25, 2025.
  • NE Schuyler Street (1200 block). Paving work to remove cavity in the street. Completed Aug. 14, 2025.
  • NE Schuyler Street (1200 block). Remove tree roots to improve drainage. Completed Aug. 26, 2025.
  • NE Siskiyou Street (7th to 17th avenues). Street grind and repave. Completed April 13-22, 2026.
  • NE Victoria Street (1600 block). Street grind and repave. Completed July 19, 2025.
  • NE Weidler Street (NE 15th Avenue to NE 24th Avenue). Street grind and repave. Completed July 7-17, 2025.

Northwest Portland

  • NW 23rd Avenue (Northrup to Vaughn streets). Grind and repave. Completed May 2026.
  • NW 24th Avenue (600 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Aug. 20, 2025.
  • NW 24th Avenue (700 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed July 21-22, 2025.
  • NW 24th Avenue (800 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed July 23-24, 2025.
  • NW 24th Avenue (900 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed July 28-29, 2025.
  • NW 24th Avenue (1000 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Aug. 13-14, 2025.
  • NW 24th Avenue (1100 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Aug. 18-19, 2025.
  • NW 24th Avenue (1200 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Aug. 21-25, 2025.
  • NW 24th Avenue (1300 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Aug. 26-Sept 25, 2025.
  • NW 24th Avenue (1400 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Sept. 4-9, 2025.
  • NW 24th Avenue (1500 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Sept 10-16, 2025.
  • NW 24th Avenue (1700 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Sept 16-18, 2025.
  • NW 24th Avenue (1400 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Oct 22, 2025.
  • NW 24th Avenue (1800 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Oct 27, 2025.
  • NW Cornell Road at tunnels (Westover Street to 53rd Ave). Remove broken culvert pipe, restore and pave road. Completed Oct 4-20, 2025.
  • NW Lovejoy Street (2500 block). Paving work to remove cavity in the street. Completed Oct 7-8, 2025.
  • NW St Helens Road (4400 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 3-4, 2025.
  • NW St Helens Road (2600 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 4-5, 2025.
  • NW St Helens Road (3600 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 5-6, 2025.

Southeast Portland

  • SE 9th Avenue and Madison Street. Paving work to backfill gaps after separate ADA curb ramp work. Completed April 27-30 2026.
  • SE 10th Avenue and Madison Street. Paving work to backfill gaps after separate ADA curb ramp work. Completed April 20-23, 2026.
  • SE 26th Avenue (3000 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Aug. 12, 2025.
  • SE 41st Avenue (2900 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Nov 25, 2025.
  • SE 41st Avenue (Woodward Street to Grant Court). Grive and repave. Funded through Fixing Our Streets. Completed May 2026.
  • SE 42nd Avenue (6900 block). Paving work to eliminate potholes. Completed Sept 23-30, 2025.
  • SE 59th Avenue (3000 block). Pave back water main. Completed July 7-8, 2025.
  • SE 70th Avenue (2800 block). Paving work to remove cavity in the street. Completed July 8, 2025.
  • SE 76th Avenue (5200 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Oct 29-Nov 3, 2025.
  • SE 77th Avenue (5500 block). Paving work to eliminate potholes. Completed Sept 22, 2025.
  • SE 100th Avenue (5400 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Sept. 22-23, 2025.
  • SE 100th Avenue (5500 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Sept. 23-24, 2025.
  • SE 100th Avenue (5300 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Oct. 1-2, 2025.
  • SE 100th Avenue (Harold to Steele streets). Street grind and repave. Completed Sept 30 - Oct 30, 2025.
  • SE 111th Avenue (100 block). Crack Seal preventive maintenance of road surface. Completed July 31-Aug. 5, 2025.
  • SE 111th Avenue (1900 block). Crack Seal preventive maintenance of road surface. Completed Aug. 27, 2025.
  • SE 112th Avenue (500 block). Crack Seal preventive maintenance of road surface. Completed Aug. 12, 025.
  • SE 112th Avenue (600 block). Crack Seal preventive maintenance of road surface. Completed Aug. 8-9, 2025.
  • SE 113th Avenue (500 block). Crack Seal preventive maintenance of road surface. Completed Aug. 20-28, 2025.
  • SE 119th Avenue (500 block). Crack Seal preventive maintenance of road surface. Completed Aug. 7-12, 2025.
  • SE Alder Street (11900 block). Crack Seal preventive maintenance of road surface. Completed Aug. 27, 2025.
  • SE Evergreen Street (4200 block). Paving work to eliminate potholes. Completed Sept 30, 2025.
  • SE Grand Avenue (800 block). Paving work to remove cavity in the street. Completed Aug. 4, 2025.
  • SE Johnson Creek Boulevard (32nd to 45th Place). Crack seal preventive maintenance of road surface. Completed Aug. 1, 2025.
  • SE Madison Street (11000 block). Crack Seal preventive maintenance of road surface. Completed Aug. 28, 2025.
  • SE Milwaukie Avenue (6500 block). Paving work to eliminate potholes. Completed July 2, 2025.
  • SE Mitchell Street (5200 block). Paving work to eliminate potholes. Completed Sept 18, 2025.
  • SE Pince Court (11300 block). Crack seal preventive maintenance of road surface. Completed Aug. 6-9, 2025.
  • SE Washington Street (82nd to 92nd Avenue). Street grind and repave. Completed Aug. 18-26, 2025.
  • SE Washington Street (8400 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Aug. 7-8, 2025.
  • SE Washington Street (11900 block). Crack Seal preventive maintenance of road surface. Completed Aug. 6-14, 2025.
  • SE Woodstock Boulevard (6900 block). Install speed bumps. Completed July 1, 2025.

Southwest Portland

  • SW 6th Avenue (2100 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Oct 1-2, 2025.
  • SW 6th Avenue (2400 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Oct 8, 2025.
  • SW 6th Avenue (I-405 ramp to Jackson Street). Paving work to eliminate potholes. Completed Oct 15-16, 2025.
  • SW 6th Avenue (Sheridan Street to Broadway). Street grind and repave. Completed. Oct 20-23, 2025.
  • SW 8th Avenue (1 block). Crack seal preventive maintenance of road surface. Completed July 24, 2025.
  • SW 10th Avenue (7000 block). Paving work to remove cavity in the street. Completed Aug. 20, 2025.
  • SW 62nd Avenue (8000 block). Remove tree roots to improve drainage. Completed July 21, 2025.
  • SW 63rd Avenue (6700 Block). Pave back water main. Completed Sept 15, 2025.
  • SW Arnold Street (2800 block). Install speed bumps. Completed Aug. 7, 2025.
  • SW Clara Lane (east of Orchard Hill Road). Pave back water main. Completed July 9-10, 2025.
  • SW Corbett Avenue and SW Nebraska Street. Pave back water main. Completed Oct 15, 2025.
  • SW Harvey Milk Street (1200 block). Paving work to backfill gaps after separate ADA curb ramp work. Completed Aug. 10, 2025.
  • SW Harvey Milk Street (12th to 13th). Street grind and repave. Completed Aug. 11-12, 2025.
  • SW High Street (1700 block). Paving work to remove cavity in the street. Completed Aug. 21, 2025.
  • SW Illinois Street (3100 block). Paving work to eliminate potholes. Completed Sept 3-4, 2025.
  • SW Luray Circus Terrace (3000). Paving work to repair concrete street. Completed Sept 15, 2025.
  • SW Market Street Drive (2200 block). Paving work to repair concrete street. Completed Aug. 18-20, 2025.
  • SW Orchard Hill Road (2700 block). Pave back water main. Completed Nov 6-19, 2025.
  • SW Pendleton Street (200 block). Paving work to remove cavity in the street. Completed July 28- Aug. 5, 2025.
  • SW Quail Post and Lancaster roads. Pave back water main. Completed July 28-30, 2025.
  • SW Taylors Ferry Road (6500 block). Paving work to eliminate potholes. Completed Sept 2-3, 2025.
  • SW Taylors Ferry Road (2600 block). Paving work to eliminate potholes. Completed Sept 4-8, 2025.

Contact

PBOT Customer Service (by PDX 311)

311Information and customer service
503-823-4000Every day, 7 a.m. to 6 p.m. (excluding federal holidays) Interpretation available | Interpretación disponible | Phiên dịch có sẵn | 提供口译服务 | Доступна интерпретация | Tafsiir la heli karo | Доступний переклад
711Oregon Relay Service

Follow on social media

Back to top