Update on North Going Street Bridge repairs

News Article
Published
Updated
In this article

Map of Going St Bridge

Fourth lane potentially in several months

News media contact:

Dylan Rivera
Portland Bureau of Transportation
503-823-3723
dylan.rivera@portlandoregon.gov
@PBOTinfo

(Oct. 14, 2019) The Portland Bureau of Transportation (PBOT) continues to work on short-term and long-term fixes to restore access for travel on the North Going Street Bridge, which provides access to the Swan Island industrial area.

The Portland City Council gave emergency approval on Sept. 25 for a contract of up to $1 million with Cascade Bridge LLC to provide bridge stabilization and repair work, including permanent repairs.

City Council members and the public have been asking about who would pay to repair the City's bridge, from the damage caused by the Union Pacific Railroad derailment Sept. 7.

The City’s Risk Management team will seek to recover from Union Pacific all reasonable and necessary costs associated with the damage to the City’s transportation infrastructure, as well as other costs related to the incident and the resulting disruptions.

Fourth lane coming soon

PBOT engineers and contractors are planning on how they can open a fourth lane on the bridge, which would allow two lanes on and off the island in each direction at all times. PBOT is working with Union Pacific to schedule times when the railroad can be shut down to allow access for bridge repairs.

PBOT has submitted a variety of work plans and schedules that could complete the work. PBOT's contractor has agreed to work at night to expedite opening a fourth lane, and while we are hoping to have the lane open as soon as possible, it could take several months because of limited access to the work zone beneath the bridge.

PBOT has also submitted a work plan that could open a fourth lane in a matter of weeks. Union Pacific is reviewing that plan.

Traffic signal adjusted for eastbound traffic congestion

People who work on Swan Island say that traffic congestion leaving the island continues to be a significant disruption. In the days after the Sept. 7 derailment, crews adjusted traffic signals. Last week, PBOT traffic engineers also adjusted the traffic signal at the intersection of N Going Street and N Port Center Way, the last signal travelers reach before they enter the bridge. The adjustments increased the "green time" for eastbound traffic by more than 30 percent, giving more time for eastbound travelers.

After the adjustment, PBOT staff measured the time it takes to travel from where the N Anchor Street ramp enters N Channel Avenue, to the point where N Channel Avenue passes under the N Greeley Avenue Bridge. At 11 a.m., without traffic congestion, the average travel time was 1 minute and 7 seconds.

Using the worst set of travel times, the average peak travel time was about 4 minutes longer than non-peak.  We did have one trip that was an increase of almost 9 minutes longer, for a trip of about 10 minutes long.

PBOT engineers will continue to look for ways to reduce traffic delays during the lane closures.

Return to six lanes potentially this spring

Planning for permanent repairs to the bridge, including planning for access to Union Pacific's property during construction, is on-going. Permanent repairs would return the bridge to its full three lanes each direction.

Permanent repairs, which would open six total lanes, could potentially be completed this spring.

Reversible lane too risky, unsafe

Initial repairs by PBOT crews made the bridge safe enough that the bureau was able to open a third travel lane on Sunday Sept. 15, allowing two lanes for westbound travel to Swan Island, with one lane available for eastbound travel. People who work on Swan Island say that traffic congestion leaving the island continues to be a significant disruption.

PBOT traffic engineers studied the feasibility of reversing the direction of one of the two westbound travel lanes, to offer two lanes eastbound direction, coming off the island, in the afternoon and evening. That option was determined to be unsafe. To use a concrete barrier to separate traffic would require obtaining specialized machinery that is not available in the region. Using cones and other plastic materials would pose safety risks as those materials could be displaced or blown over by traffic, blocking travel lanes. Moving plastic materials twice a day also exposes city crews or contractors to safety risks during the most hazardous time of a road closure: the time when they make adjustments to the equipment at the scene.

Work starting soon on N Greeley Avenue will close a northbound lane

The team working on the North Going Street Bridge has been coordinating with another PBOT team and a contractor that is starting work on repaving North Greeley Avenue. The North Greeley Multiuse Path and Paving Project will soon require closing one lane northbound on Greeley, at a location closest to N Interstate Avenue and far enough away that it should not impact traffic entering the North Going Street Bridge. Lean more at this North Greeley project update. 

Stay tuned for further updates

We will continue to provide updates as more information becomes available.

Sign up here for email or text message updates about the repairs to the North Going Street Bridge and access to Swan Island
Image removed.
Sign up to receive PBOT's citywide traffic advisories by email or text message, and monitor our Twitter account @PBOTinfo for breaking news and alerts

For more information:

Dan Layden
Project Manager
dan.layden@portlandoregon.gov
503-823-2804

Image removed.

The Portland Bureau of Transportation (PBOT) is the steward of the City’s transportation system, and a community partner in shaping a livable city. We plan, build, manage and maintain an effective and safe transportation system that provides access and mobility. www.portlandoregon.gov/transportation