Homestead

Construction and Maintenance

Council Crest Sewer and Stormwater Project

Sewer And Stormwater
Active
This project is in an early evaluation and information gathering phase. Design for the project will likely not begin until 2021. Construction is not expected until 2022 or later.

Sheridan Trunk Sewer Project-Duniway Park

Sewer And Stormwater
Active
Design started in March 2021 and will continue over the next two years. Construction is currently scheduled to begin May 2023 and will take up to a year to complete.

SW Menefee Sewer Extension Project

Sewer And Stormwater
Active
Design on this project will take place from May 2020 – April 2021. Construction is expected to begin in late Spring of 2021. Sewer construction work will take about three weeks to complete.

Replacing the motor control centers at the Barbur Gibbs Pump Station

Water System Improvement Construction
Upcoming
Fall 2021 to Winter 2022
Summer 2022