Environmental Review
When Environmental Review is required
You need an Environmental Review if:
Your project is in an environmental overlay zone and:
- Cannot meet one or more development standards
- Your project is not exempt
- You need to correct a violation of environmental regulations
If you're unsure, talk with a planner early. Not meeting a standard is the most common reason you'll need a review.
Application requirements
Your Environmental Review application must include a written narrative and site plans.
Get the detailed list of requirements:
Please refer to the City Code chapter, Environmental Zones 33.430, for approval criteria and requirement details.
Written narrative
Your narrative must explain:
- Which standards your project cannot meet
- How the project meets applicable approval criteria from 33.430.250. As part of addressing the approval criteria, you will need to explain:
- How your project affects natural resources (e.g., impact evaluation)
- What alternatives you considered and why you chose the least-impactful option
- How construction will be managed to minimize disturbance
- How you will mitigate impacts, including required plantings and restoration
The narrative must include:
- Impact Evaluation: Explain the natural resources on your site and how your project could affect them.
- Find the natural resource inventory for your site.
- Find the natural resource inventory for your site.
- Alternatives Analysis: Show that you considered different layouts, locations, and construction methods. You must choose the alternative that is practicable and causes the least impact.
- Construction Management Plan: Describe how you will protect trees, soils, slopes, and water features during construction, both in writing and with a plan drawing.
Tree protection must follow Title 11 requirements and may require input from a certified arborist.
- Mitigation Plan: Describe how you will offset the remaining impacts. Mitigation must replace the types of resources you are affecting.
The mitigation area must be larger than the disturbance area. This accounts for the time it takes for the mitigation to provide the same level of environmental functions.
Required site plans
You must submit the following plans:
- Existing conditions
- The location of all e‑zone boundaries
- Conditions before a violation (if applicable)
- Proposed development
- Construction management
- Mitigation or remediation
Each plan has specific requirements listed in 33.430.240.A.
Do you need a professional?
You may be able to prepare the application yourself if you understand local natural resources and know how to prepare detailed site plans.
Many homeowners choose to work with a professional environmental consultant, engineer, planner, or architect because it can save time and reduce back‑and‑forth with reviewers.
How to apply
To apply for Environmental Review, submit:
- The land use review application form
- The required fee
- Your narrative and site plans
- Any other items listed in the application checklist
Application form:
Fee schedules: Land use services fees
Submit your materials following the instructions on the Land Use Reviews and Final Plat Applications webpage.
Environmental Review process
Different types of projects follow different procedures depending on their complexity:
- Type II Review: Most Environmental Reviews and most violation-related reviews use this process.
- Type Ix Review: Used for property line adjustments, public recreational trails, and resource enhancement projects.
- Type III Review: Used for projects in the Environmental Protection (p) zone and some complex violation corrections.
- For Type III Review, a Pre-Application Conference is required before applying. These meetings are valid for two years.
Optional, but highly recommended: Request an Early Assistance appointment before applying for Environmental Review. It can help find any major issues that could affect your project.
For more information on review types and requirements, visit: Land Use Review types and fees
After Environmental Review is complete, what comes next?
The Environmental Review decision is not a permit for the work.
You must apply for required permits before you start work.
Your permit application must be consistent with the plans approved through the Environmental Review and document how conditions of approval are met.
Resources
Map environmental zoning lines on your property (required for site plan)
Find the natural resource inventory that applies to your property (required for the written narrative)
- Go to the Open Data Portal Resource Sites.
- Find your property on the map and click on it.
- A data window will pop up:
- The GeographicPlanArea field shows which natural resource inventory applies to your site.
- The Site_Label field shows the specific resource site for your property.
- Go to the Environmental and River Planning Documents page.
- Find the document using the GeographicPlanArea.
- Within the document, search for the specific resource site using the Site_Label.
Native plants approved for use in e-zones
The Portland Plant List is an extensive list of native plants and the various Portland plant communities.
All vegetation planted in environmental zone resource areas must be native species as identified on the Portland Plant List.
Meet mitigation monitoring requirements
Landscape monitoring is often required as a condition of approval for environmental reviews with mitigation plantings.