information
Portland and the federal government

Learn about our sanctuary city status, efforts to block federal overreach: Portland.gov/Federal

Residential Inspections: The Start-to-Finish Guide

Information
Your project may need inspections at different stages—before, during, and after the work. This guide shows you exactly when to schedule inspections and what steps to take. We’ll walk you through the requirements and help you get ready so your inspections go smoothly.

The City of Portland requires residential inspections for one- and two-family homes. This includes duplexes and two-unit townhomes.

Your permit is not complete until an inspector approves the work.

Before you start work

  • Know your responsibilities
    • You, the permit holder, are legally responsible for all permitted work, required inspections, and overall project coordination.
    • Consider hiring a licensed contractor
      • If you're not familiar with construction codes or inspection requirements, a licensed contractor can help you avoid costly delays and mistakes.
    • Highly recommended: We're here to help with pre-construction Consultations.
       
  • Review your approved plans for special requirements
    • Check your permit documents for any of the following:

      • Tree preservation requirements
        • For projects that require tree preservation, a Root Protection Zone must be set up.
        • Before starting any ground-disturbing activities, get a Tree Preservation Inspection (507). 
           
      • Special inspections
        • Special inspections (e.g., structural, soils) are identified in your approved plan set. If you're unsure whether they apply to your project, stop and confirm before proceeding. Work performed without the required special inspection oversight may need to be removed and redone.
           
      • Deferred submittals
        • All deferred submittals must be submitted and approved before continuing with the portion of work they affect. Proceeding without approval can result in failed inspections and delays.
           
      • Cesspool decommissioning
        • If your project site includes a cesspool or other private sewage disposal system, it must be properly decommissioned in accordance with Oregon DEQ regulations and City of Portland requirements.


       

  • Get the required trade permits (if you didn't get a combination permit)
    • If your project includes any of the following types of work, you must obtain separate trade permits:
    • Important for property owners:
      • If you own the property and plan to do the trade work yourself, you can get the required trade permits as a homeowner. This only applies if the building is not for sale, lease, or rent.
      • If you hire a subcontractor to do the work, they must get their own permits.
         
  • Keep approved plans on site
    • Plans must be available on site for all inspections throughout the project.
       
  • Do not cover work without an inspection
    • All permitted work must be inspected before it is covered by drywall, concrete, backfill, etc.
       
  • When in doubt, call for an inspection
    • It’s better to call than to risk delays or rework.

Need technical advice? Contact inspectors about residential permits.


Overview of scheduling inspections

Inspections must be requested in a specific order to ensure code compliance and prevent delays.

  • Schedule a pre-construction Consultation Inspection. This is an optional inspection, but it is highly recommended to avoid costly rework.

    We will review your approved plans and clarify all the required inspections you'll need to schedule.

    • The Consultation Inspection is included with your approved permit. There's no additional cost for this consultation.
    • Schedule before you start any work.
    • To schedule a consultation inspection, use the following codes to request a consultation by discipline:
      • 295 – Structural
      • 155 – Electrical
      • 397 – Plumbing
      • 650 – Mechanical
    • How it works:
      • An inspector will call you between 7:30 a.m. and 8:30 a.m. on the day of your scheduled consultation to determine whether your question can be resolved over the phone or if an on-site visit is needed.
      • Keep approved plans on site.
      • Important: Consultations do not count as approved inspections. All required inspections must still be scheduled and passed for the work to be approved.

     

  • You may schedule multiple inspections on the same day. We’ll assign them to the same inspector when possible.
     
  • Important: All rough trade inspections (electrical, plumbing, mechanical) must be approved before the 270 Framing inspection can occur.

Inspection sequences by project types

Alterations and conversions

Applies to interior remodels, garage/attic/basement conversions, and changes of use.

Only schedule inspections relevant to the scope of work performed.

Find inspection details and when to schedule.

Typical inspections for alterations and conversions include:

  • 105 - Electrical Rough-In
  • 310 - Plumbing Rough-In / Top-Out
  • 620 - Mechanical Rough-In
  • 260 / 270 - Shear Wall / Framing (if structural changes occur)
  • 280 - Insulation
  • 199/399/699 - Trade Finals
  • 299 / 999 - Final Building / Final Permit

All permits need the “999 Final Permit” inspection. Your permit will not be approved and closed until you get this inspection. Without the “999 Final Permit” inspection, the permit is still “under inspection.” If a permit is without an approved inspection for more than 180 days, it will expire.

Get the full list of inspections.

Additions and new construction

New construction: Full inspection sequence (applies to new builds from the ground up). Follow the full inspection sequence (listed below) starting with erosion control and foundation, continuing through rough-in phases, and ending with final inspections.

Additions: Full inspection sequence (applies to adding new square footage to an existing structure). Follow the full inspection sequence (listed below) starting with erosion control and foundation, continuing through rough-in phases, and ending with final inspections for the new portion of the building.

Full inspection sequence

Find inspection details and when to schedule.

  • Foundation phase inspections:
    • 507 - Tree Preservation (if required – check the approved site plan)
    • 200 - Pre-construction Erosion Control
    • 215 - Setbacks / Location on Lot (May require a survey if original property corner pins are not visible)
    • 220 - Footings
    • 225 - Foundation Walls
    • 235 - Slab-on-Grade
    • 305 - Underground Plumbing
    • 238 - Radon Mitigation System
       
  • Underfloor / post and beam / site utilities phase inspections:
    • 305 - Underground Plumbing (if not already inspected)
    • 600 - Mechanical Underfloor / Post and Beam
    • 240 - Underfloor Inspection (prior to subfloor installation)
    • 110 -Underground Electrical
    • 345 - Water Service
    • 350 - Sanitary Sewer
    • 355 - Storm Sewer
    • 365 - Rain Drains
       
  • Framing / rough-in / cover phase inspections:
    • 310 - Rough-in / Top-out Plumbing
    • 315 - Shower Pan (when holding water)
    • 320 - Fire Sprinklers
    • 105 - Rough Electrical
    • 120 - Permanent Service
    • 107 - Electrical Floor Heat
    • 620 - Rough Mechanical
    • 617 - Hydronic Heating
    • 260 - Shear Wall Nailing
    • 265 - Firewall Nailing (if required on plans; must occur before mudding and taping)
    • 270 - Framing (moisture content form required)
    • 280 - Insulation
       
  • Additional inspections (as required — check plan set):
    • 487 - Stormwater Management
    • 842 -Cesspool Decommissioning
       
  • Final phase requirements and inspections:
    • Before scheduling a Final 299 or 999 inspection, complete the following:

      Schedule final inspections:

      • 199 - Final Electrical (all devices installed and operational)
      • 399 - Final Plumbing (all fixtures in place and working)
      • 699 - Final Mechanical (HVAC systems complete and functional)
      • 299 - Final Building (Address posted, smoke/CO detectors, handrails, egress, required finishes, decks, etc.)
      • 999 - Final Permit (closes the permit officially)

      All permits need the “999 Final Permit” inspection. Your permit will not be approved and closed until you get this inspection. Without the “999 Final Permit” inspection, the permit is still “under inspection.” If a permit is without an approved inspection for more than 180 days, it will expire.

Get the full list of inspections.


When to schedule inspections

Tree preservation (when required)

Protection must be in place and be approved before ANY other work takes place. 

Protected trees need a 6-foot chain-link fence around them as detailed in the approved plans.

Erosion control

If you are disturbing the ground, you need to have erosion control measures installed, inspected and approved.

The erosion control inspection must happen before beginning any further ground-disturbing activities.

Footing and setback inspections

  • After trenches or pad openings are excavated and cleared of loose material or mud.
  • After any fill materials are placed, forms erected and secured in place, and reinforcing is in place and secured.
  • Before placing concrete.
  • New construction requires a grounding electrode to be in place before inspection.
  • Property lines must be identified by finding the existing official corner markers or providing a property survey for inspection of the setbacks and fire separation distance between the lot lines and new construction.
  • We strongly recommend that you allow 24 hours from the time of your inspection to your pour to allow for corrections and re-inspections.

Foundation inspection

  • After forms and reinforcing are erected and secured or braced. Before placing concrete.
  • All hold-downs and special frame anchor bolts must be mounted in place before inspection.
  • Can be combined with the footing inspection
  • We strongly recommend that you allow 24 hours from the time of your inspection to your pour to allow for corrections and re-inspections.

Under-floor or electrical, plumbing, and mechanical inspection

  • Any plumbing, electrical, mechanical, and gas piping work that will be installed under the floor.
  • After the electrical, plumbing, ductwork, and gas piping are in place and secured but before covering the floor framing.
  • Mechanical and plumbing inspections may be done at the same time as the under-floor framing inspection.

Under-floor or post and beam inspection

  • After all under-floor plumbing, electrical, and mechanical (including gas pipe) systems have been installed
  • After all sill plates and underfloor structural components are in place secured and properly fastened
  • Before the application of flooring or insulation materials.
  • All structural components which have been improperly cut or notched for plumbing, etc. are to be repaired or replaced as needed.

Concrete floor slabs inspection (within buildings/structures)

  • After all under-floor plumbing, electrical, and mechanical systems have been installed and approved
  • After the ground surface is prepared and leveled, forms are in place and secured, reinforcing or woven wire mesh (if required) and under-slab insulation (when required) are in place.
  • We strongly recommend that you allow 24 hours from the time of your inspection to your pour to allow for corrections and re-inspections.

Roof coverings inspection

The roof covering may be installed over the roof sheathing at any time unless otherwise noted on your plans.

Rough-in inspection, all systems (rough plumbing, electrical, mechanical, and gas piping system)

  • Before the framing inspection and covering any work.
  • Can be done at the same time as the framing inspection.

Shear walls inspection

  • After the structural frame is in place, all panels are to be nailed per the shear wall schedules, hold-downs and straps are to be installed and in any miscellaneous attachments installed.
  • Can be done with the structural frame inspection.

Structural frame inspection

After approval of all the above systems. 

  • All structural components that have been improperly cut, notched, or altered for systems installations must be replaced or repaired as indicated.
  • Roof, wall, and floor sheathing are to be in place and nailed.
  • Bracing, blocking and fire stops are to be complete.
  • Windows and doors must be installed.

Insulation and vapor barrier inspection

  • After all insulation and vapor barriers are in place and secured.
  • Includes walls, floor, ground covers etc.
  • Does not include loose insulation to be supported by ceiling finish materials.

Weather protection must be provided before insulation. Wet or soaked insulation will be rejected. Substantially wet or soaked wood construction is not to be covered with vapor barriers unless adequate provisions are made for thorough drying of the structure.

Under-floor and attic insulation may be done at a later time, but must be in place before the final inspection.

Gypsum wallboard (drywall) inspection (on firewalls and gypsum wallboard/drywall shear walls only)

  • After all nailing or other fastening systems are complete.
  • Before tape, plaster, or other coverings are applied.
  • If multiple layer of gypsum wallboard are required, the nailing of each layer must be inspected.

Public sidewalk and driveway approach inspection

  • Required for all concrete paving within the street right-of-way.
  • After the excavation is complete, the forms are in place and secured, and the sub grade is properly prepared.
  • Before placing of any concrete.
  • The Portland Bureau of Transportation (PBOT) performs ALL driveway aprons and frontage sidewalks. Please call (503) 823-7002 to schedule inspections for this part of your project.
  • Portland Permitting & Development will continue to inspect the flatwork part of the driveway from the back of the sidewalk to the garage/house. Please call (503) 823-7000 to schedule the inspections for this part of your project.

Driveways, porches, and flat work inspections (concrete driveways, patios, walkways, and porches)

  • After the ground service is prepared and leveled, and forms are in place and secured.
  • The inspector will verify that the placement of concrete will not be against untreated framing or siding, and the rise and run of any steps or stairs.
  • We strongly recommend that you allow 24 hours from the time of your inspection to your pour to allow for corrections and re-inspections.

Other inspections

Other inspections may be required on particular jobs. These inspections will be on the approved plans and specifications. The building inspector will let you know if you need any other inspections.

Special inspections

Special inspections monitor specific critical structural materials that require the attention of professionals with specialized skills and qualifications. 

When special inspections are required, a qualified and approved special inspector is to be at the job site whenever work requiring special inspections is in progress. 

The City of Portland does not perform special inspections. The building inspector or approved agency will submit a report of their findings upon completion of the inspection.

The Oregon Building Officials Association has created a list of approved special inspectors and agencies.

Final inspections

After all other required inspections are approved including:

  • building
  • electrical
  • plumbing
  • mechanical
  • erosion control
  • tree planting (if required)
  • fire suppression (if required) 

Must have final approval before occupancy of the premises is allowed. 

All permits need the “999 Final Permit” inspection. Your permit will not be approved and closed until you get this inspection. Without the “999 Final Permit” inspection, the permit is still “under inspection.” If a permit is without an approved inspection for more than 180 days, it will expire.


Schedule an inspection

Schedule on DevHub or over the phone with our automated system.

If you need to cancel an inspection:

  1. Sign into DevHub.
  2. Open the Inspections section.
  3. Select the Cancel button for the inspection, then confirm the cancellation. 

Today's scheduled residential inspections

Learn about today's residential inspections.


Inspection results

Your inspector will email you an inspection report. If the inspection is approved, great!

If the inspection failed, then your inspection report will list the corrections required to get approved.

There are many reasons why the work did not get approved:

  • No access - the inspector may not have been able to inspect the work
  • incomplete work
  • code violations

You will be responsible for making the corrections.

You can also get inspection results by searching for your permit on DevHub.


Re-inspections

Option 1 (fastest option): Schedule through Remote Video Re-inspections (RVR)

Option 2: Schedule through DevHub

Log in to DevHub, click the Inspections button, and enter your IVR or permit numbers.

Learn more about scheduling inspections through DevHub.

Option 3: Schedule through IVR

Call for a re-inspection at 503-823-7000 after making the corrections. Use the same three-digit inspection code.

If you make the corrections the same day, wait until 5 pm to request a re-inspection. The inspector needs to enter their results before you can schedule the re-inspection.


Contact inspectors about residential permits

If you have questions after a previous inspection, find your inspector's contact information on your inspection results or PortlandMaps.

For technical code advice, contact the senior residential inspectors.

Senior Residential Inspectors
Sr. Building Inspector503-823-8471
Sr. Building Inspector503-823-8239
Sr. Building Inspector/Expired Permits 503-823-8722
Sr. Electrical Inspector503-823-8481
Sr. Plumbing Inspector 503-823-8630
Sr. Mechanical Inspector503-823-8497

For Remove Video Re-inspection (RVR) help, call 503-823-8426.

For all other questions, call Office Support at 503-823-7388.

The inspectors' names and regions are listed on the 1 & 2-Family Residential Inspector District Map. Your inspector may be different than the one listed on the map.

Contact

General Inquiries

Portland Permitting & Development
phone number503-823-7300The phone is answered Monday through Friday from 8 a.m. to 5 p.m. Please leave a message if you call outside of those hours.
Oregon Relay Service711Oregon Relay Service

Requests for Inspection

Permitting & Development
phone number503-823-7000Automated Line - Requires an IVR or permit number
Oregon Relay Service711Oregon Relay Service

Residential Inspections

Permitting & Development
phone number503-823-7388Monday through Friday from 8:15 a.m. to 3:45 p.m.
Oregon Relay Service711Oregon Relay Service
fax number503-823-7693

Property Compliance Help Line

Permitting & Development
phone number503-823-2633Monday through Friday from 8 a.m. to 4 p.m.
Oregon Relay Service711Oregon Relay Service
Back to top