Montgomery Park Streetcar Extension

ស្លាក: Information
The Portland Bureau of Transportation (PBOT) is designing an extension of Portland Streetcar to Montgomery Park in Northwest Portland. The extension will run along NW 23rd Avenue and add a new one-way couplet along NW Roosevelt and Wilson streets, serving a new mixed-use district west of Highway 30.

Overview

The project also includes rehabilitation of NW 23rd Avenue between NW Vaughn and NW Northrup streets, removing old trolley tracks, replacing aging underground utilities, and upgrading curb ramps. New street extensions of NW Roosevelt Street, NW Wilson Street, and NW 25th Avenue will improve connections for people walking, rolling, biking, and driving in the new district. As part of the project, the City of Portland is purchasing up to 10 new hybrid streetcar vehicles to support the extension and broader system operations. The project is now in the project development phase, with construction expected to begin in 2029. 


Project map

 


Project timeline

The project still has many elements left to be designed before construction begins in 2029. 

  • Project design has started and will be completed in 2028.
  • Construction is anticipated to take two years, from 2029 to 2031.
  • Open for service in 2031 for trips to Montgomery Park!

What's happening now?

The project team is working on advancing design, with the preliminary (30%) design set expected by the end of 2026. In the interim, the team is working to reintroduce the project to community members. More information about public engagement is available below. 


Sign up for email updates

Click here to sign up for email updates


Public engagement

Public engagement for this project kicked off in 2007, with formal area planning for the project occurring between 2019 and 2024. Engagement has included many productive community conversations since that time. Read more about previous engagement here.

Learn more about previous engagement

Public engagement for the current project development phase began in September 2026. The project team will host open houses at key design milestones and host information tables at local events to keep the community informed and involved. You can learn more in the Fall 2026 Community Outreach Plan.

Review the Fall 2026 Engagement Strategy 

Upcoming events

The project team is planning to canvas along the extension in Fall 2026 and the first project Open House for preliminary design (30%) in early 2027. 

Updates regarding the public engagement schedule will be posted on this webpage and sent via email updates. Please check back as the project advances or sign up for email updates to stay informed. 

Additional resources

  • If you have any questions in the meantime, you can reach out to the project team anytime at MPstreetcar@portlandoregon.gov. The project team would be happy to talk with you. 
  • Sign up for email updates to stay informed and learn about future events and engagement opportunities related to the project.
  • Review the overall project public engagement strategy here. 

Project background

The Montgomery Park Streetcar Extension was initially identified in the 2009 Portland Streetcar System Concept Plan. Since that time, extensive planning and engagement has occurred, culminating in the 2024 City Council adoption of the Montgomery Park Area Plan and adopted Locally Preferred Alternative (LPA) for the project. You can learn more about the project background and previous engagement in the Project Background and Previous Engagement Report. 

Learn more about the project background


The opportunity

For more than 20 years, the Portland Streetcar has been one of the City's tools for equitable and sustainable development. The new 1.3-mile streetcar extension to Montgomery Park and adopted land use changes will support the development of a new mixed-use district in Northwest Portland, with the potential for thousands of new housing units, including affordable housing. 

The streetcar extension will help us:

  • Connect more people via transit to critical destinations, including Forest Park, employment opportunities, healthcare, and educational opportunities in Northwest Portland, Downtown, and throughout Portland and the region
  • Reduce carbon emissions by helping people meet their daily needs without a personal automobile
  • Expand Streetcar access to diverse riders who rely every day on transit to get to important destinations
  • Provide zero-emission, high capacity transit to future residents, employees, and visitors of a new mixed-use district west of Highway 30
  • Rehabilitate NW 23rd Avenue from NW Lovejoy Street to NW Vaughn Street, supporting the vitality of one of Northwest Portland's most vibrant streets

Key facts

While the project is still being designed, some key issues regarding the streetcar extension include:

  • Parking: Parking loss along NW 23rd Avenue will be as minimal as possible. However, some parking loss will occur near accessibility upgrades, at station locations, and in some areas with atypical cross sections due to right-of-way constraints. 
  • Right-of-way: The streetcar will be able to fit within the right-of-way on NW 23rd Avenue, with minimal impacts to travel lanes. Parking will be maintained on both sides of the street.
  • Loading zones: Due to constraints, loading zones are not currently planned on NW 23rd Avenue but can be included as needed on nearby side streets. None currently exist.
  • Transit travel time: Streetcar trips are not expected to be slower and streetcar headways will not be less frequent because of the extension.
  • Off-wire extension: The new streetcar extension will be 100% off-wire utilizing proven hybrid battery technology, allowing cars to switch effortlessly between the existing streetcar system and this new extension. It will result in no new poles or overhead wires, reducing construction and ongoing maintenance costs while minimizing impacts to NW 23rd Avenue. Portland Streetcar's original fleet of vehicles are more than 25 years old and are in need of replacement. Procurement of new streetcars with off-wire capability was already planned due to this need. More information is available at the Portland Streetcar website.
  • Construction: The project team is coordinating project elements to minimize disruption as much as possible during construction, and PBOT will work to support businesses and residents during that time. Construction is expected to begin in 2029.

Project partnerships

This project is made possible with support from Metro, the Portland metropolitan area's regional government and Metropolitan Planning Organization, and TriMet, the tri-county Transit operator for the Portland metro.