See something we could improve on this page? Give website feedback.
Approval of the FY 2022-23 Budget for the City of Portland (Mayor convenes Council as Budget Committee)
TO: Mayor Ted Wheeler
Commissioner Dan Ryan
Commissioner Carmen Rubio
Commissioner Mingus Mapps
Commissioner Jo Ann Hardesty
City Auditor Mary Hull Caballero
FROM: Jessica Kinard, City Budget Director
DATE: May 3, 2022
SUBJECT: Approval of the FY 2022-23 Budget for the City of Portland
With this memo, the City Budget Office conveys a package of information to aid the Council in considering changes to the Proposed Budget and moving to an Approved Budget for submittal to the Tax Supervising and Conservation Commission (TSCC). Attached to this memo are the following documents:
- Attachment A: A step-by-step description of the process for consideration of and deliberation on changes to the FY 2022-23 Proposed Budget at the May 11th Budget Committee meeting
- Attachment B: List of all adjustments to the FY 2022-23 Proposed Budget
- Attachment C: Summary of adjustments by fund and major object category
- Attachment D: Budget Notes as Proposed for the Approved
- Attachment E: Tax increment collections planned for the City’s Urban Renewal Districts.
The City Budget Office will present these adjustments and budget notes to be incorporated into the Approved Budget subject to the vote of the Budget Committee on Wednesday, May 11, 2022. Because of the short timeframe for voting on the Approved Budget, the City Budget Office would appreciate receiving any contemplated amendments by end of business day of May 9, 2022. This will allow staff to be adequately prepared for Council discussion and action. The Council will have the opportunity to make further amendments to the budget as part of the Adopted Budget process scheduled for first reading on June 8, 2022.
Official record (Efiles)
Impact Statement
Purpose of proposed legislation and background information
The report includes changes to the FY 2022-23 Proposed Budget which must be approved by the City of Portland Budget Committee.
Financial and budgetary impacts
The action of the Budget Committee (as requested in this report) does not change total requirements in various funds as compared to the FY 2022-23 Proposed Budget, as distributed on May 5, 2022. It is expected the Approved Budget will be amended by $34.8 million in the General Fund to program out the forecasted one-time revenues from the April 2022 City Economist Forecast. These resources are currently accounted for as a one-time source in the Mayor’s Proposed Budget, but have not been programed into bureaus at present.
Community impacts and community involvement
The Approved Budget as filed includes multiple programmatic changes that will impact the community. These programmatic changes invest resources and reallocate internal resources into bureau programs as articulated in the Mayor’s Proposed Budget document. A five-member Community Budget Advisory Board was invited to sit in on budget discussions with the Mayor and Council as the budget was developed. There were seven work sessions held to discuss the FY 2022-23 Budget process between March 4-29, 2022. Council conducted two virtual listening sessions in April as well. Public comment has been solicited on the City Budget Office website, and in accordance with Oregon Local Budget Law, live public testimony is scheduled to be received on May 5th through a virtual community meeting and during the hearing date for May 11, 2022. Council members receive weekly emails from the CBO compiling the written comments received by the public through the online portal.
The budget process continues with the final opportunity for Council to amend the budget and receive public testimony and input. At present, this is scheduled to occur on June 8, 2022.
100% renewable goal
This action does not directly impact the 100% renewable goal.