Section 1. The Council finds:
- In 2017, the Portland Bureau of Transportation applied to Metro as part of the 2019-21 Regional Flexible Funds program for a federal grant in the amount $2,400,000 for design engineering and construction of the NE Halsey Street Bike/Ped/Transit Improvements Project; and
- In February 2019, through Ordinance 189401, the council approved the acceptance of a grant from the Oregon Department of Transportation to the Portland Bureau of Transportation for the design and construction of the NE Halsey Street Bike/Ped/Transit Improvements Project in the amount of $2,400,000.
- The Portland Bureau of Transportation over matched the grant with an additional $2,580,000 from the Transportation System Development Charge fund and $180,000 from General Transportation Revenue. The original total project cost was $5,160,000.
- In March of 2023, the NE Halsey Street Bike/Ped/Transit Improvements Project received $1,000,000 of Congressionally Directed Spending from the Federal Highway Administration and $1,900,000 of Highway Improvement Program funds from Metro. In November of 2023, the Project received an additional $412,118 from the Oregon Department of Transportation Bridge Program. The new total project cost is $8,472,118.
NOW, THEREFORE, the Council directs:
- The City Administrator or designee is hereby authorized to execute an Amendment to the Intergovernmental Agreement (contract 30006830) in a form substantially similar to Exhibit A.
Section 2. The Council declares that an emergency exists because a delay would unnecessarily delay the City’s ability to perform the activities authorized by the grant; therefore, this Ordinance shall be in full force and effect from and after its passage by the Council.
Official Record (Efiles)
An ordinance when passed by the Council shall be signed by the Auditor. It shall be carefully filed and preserved
in the custody of the Auditor (City Charter Chapter 2 Article 1 Section 2-122)
Passed by Council
Auditor of the City of Portland
Simone Rede
Impact Statement
Purpose of Proposed Legislation and Background Information
- To amend a federal grant and accept additional funds for construction of the NE Halsey Street Bike/Ped/Transit Improvements Project.
- The project number is T0871 and the grant number is TR000280.
Financial and Budgetary Impacts
- The IGA amendment increases federal funding for the project.
- This increase was assumed in PBOT’s FY24-25 capital improvement program.
- In March of 2023, the NE Halsey Street Bike/Ped/Transit Improvements Project received $1,000,000 of Congressionally Directed Spending from the Federal Highway Administration and $1,900,000 of Highway Improvement Program funds from Metro. In November of 2023, the Project received an additional $412,118 from the Oregon Department of Transportation Bridge Program.
Community Impacts and Community Involvement
- This project will benefit the community by providing needed transportation improvements.
- There has been extensive community involvement in both the planning and design phase of the project.
100% Renewable Goal
Not applicable.
Financial and Budget Analysis
Analysis provided by City Budget Office
This action authorizes increased federal funding for the NE Halsey St bike, pedestrian, and transit improvement project. Additions include $1,000,000 of Congressionally Directed Spending from the Federal Highway Administration and $1,900,000 of Highway Improvement Program funds from Metro. In November of 2023, the Project received an additional $412,118 from the Oregon Department of Transportation Bridge Program. These fund are assumed in PBOT's FY 2024-25 Adopted CIP.