Construction

27 projects found

Irving Park Stormwater Project

Sewer and Stormwater
Active
Nature patch work was completed in February 2021. Rain garden and green street planter design is in progress and will continue through winter 2021. Construction of the rain gardens and green street planters is currently scheduled to begin June 2022.
Environmental Services and Portland Parks & Recreation are collaborating on a project to build nature patches and rain gardens to manage stormwater in Irving Park. The project will help prevent nearby flooding, sewer basement backups, and sewage overflows into the Willamette River during storms.

Force Avenue Pump Station Project

Sewer and Stormwater
Active
Design will continue through early 2022. Construction is tentatively scheduled to begin in the spring of 2022 and take up to a year and a half to complete.
Environmental Services is designing a project to remodel the 47-year-old Force Avenue Pump Station in North Portland. Increased pumping capacity will accommodate growth and future demands on the sewer system. Improved reliability, access, and safety will protect public health and the environment.
This project is currently in design. Construction is anticipated to start in the spring or summer of 2022 and take nine months to complete.
Environmental Services is designing a project to install monitoring equipment along the Portsmouth force main sewer line on Swan Island. This system will help public sewer pipes operate efficiently and safely and prevent sewage overflows to the Willamette River.
Design is expected to continue through December 2022. Construction is expected to begin in April 2023 and take about two years to complete.
Environmental Services is designing a stormwater management project in the Portsmouth neighborhood to reduce the amount of pollution entering the Columbia Slough. This project is part of a larger effort to improve water and sediment quality in the Columbia Slough.
Construction is anticipated to begin August 2021 and be completed by March 2022.
Environmental Services will construct a project that removes 22 aging sumps throughout the City and replaces them with 17 new sumps and 10 new sedimentation manholes.