Construction
Tryon-Stephens Neighborhood Street Improvement Project- SW Galeburn: SW Capitol Highway to SW 41st Ave Street Improvement Project
Transportation
Engineering And Design
Construction: Spring 2025
PBOT will be improving several local streets in the Tryon Creek and Stephens Creek watersheds in southwest Portland by paving gravel streets, adding sidewalks or walkways, or a combination. Funding comes from the Local Transportation Infrastructure Charge (LTIC) and other sources.
Tryon-Stephens Neighborhood Street Improvement Project- SW Capitol Hill Rd
Transportation
Engineering And Design
Construction: Late Winter/Early Spring 2025
PBOT will be improving several local streets in the Tryon Creek and Stephens Creek watersheds in southwest Portland as part of SW Tryon Stephens Transportation Infrastructure Charge (LTIC) by paving gravel streets, adding sidewalks or walkways, or a combination.
Hillsdale Middle Sewer Project
Sewer and Stormwater
Active
Construction is anticipated to begin in Summer 2024 and will last a year.
Environmental Services is in the design phase of the Hillsdale Middle Sewer Project. This project will repair or replace approximately 11,897 feet of aging public sewer pipes throughout the neighborhood. Taking these actions now will help protect public health and the environment.
Hillsdale North Sewer Project
Sewer and Stormwater
Active
Construction is anticipated to begin in March 2025 and may take a year to complete.
Environmental Services is designing a project to repair approximately 8,571 feet (or 1.62 linear miles) of aging public sewer pipes throughout the Hillsdale neighborhood in Southwest Portland. Taking these actions now will help protect public health and the environment.
Hillsdale Northwest Sewer Project
Sewer and Stormwater
Active
Construction is anticipated to begin in Spring 2025 and take a year and a half to complete.
Environmental Services, your sewer and stormwater utility, is beginning the design stage of the Hillsdale Northwest Sewer Project. This project will repair or replace approximately 8,313 feet of 100–120-year-old public sewer pipes throughout your neighborhood.
Fulton Pump Mains Replacement
Capital Improvement Project
Engineering And Design
Fall 2024 to Fall 2025
The Water Bureau will install 3,350 feet of water main (pipe) in southwest Portland. The pipes are aging and pass underneath the I-5 freeway and SW Barbur Boulevard, where a failure of these older pipes could cause major problems. This project will benefit over 42,000 people served by the main.
Barbur Apartments
Rental
In Planning
Fall 2026
Innovative Housing, Inc. will develop 149 units of affordable housing in the SW Corridor serving individuals, families, people with disabilities, and households displaced by the proposed future light rail.
Marquam Nature Park Sewer and Stormwater Planning Project
Sewer and Stormwater
In Planning
The Bureau of Environmental Services is investigating conditions of the stormwater system in Marquam Park & Council Crest and exploring options for improvement and rehabilitation. This project will help ensure that stormwater and sewer systems in the area have adequate capacity in major storms.
Gooseberry Trails
Home Ownership
In Planning
Summer 2026
Habitat for Humanity will develop 52 newly constructed townhomes ranging from 2 to 5 bedrooms, prioritizing large and multi-generational families. Through a partnership with Proud Ground, the developed land will be held in a community land trust.
SW Bertha Boulevard (SW Vermont St. to SW Barbur Blvd.)
Transportation
Engineering And Design
–
The Portland Bureau of Transportation (PBOT) will reconfigure this roadway as a protected bike lane. The project limits are along S Bertha Blvd. from SW Vermont St. to SW Barbur Blvd. The intent is to reorganize the roadway to provide protected bike lanes.