5.34.120 Selection of Substitute Contractor.

City Code Section
  1. If a Contractor provided a performance bond, the City may afford the Contractor's surety the opportunity to provide a substitute Contractor to complete performance of the Contract. A substitute Contractor shall perform all remaining Contract Work and comply with all terms and conditions of the Contract, including the provisions of the performance bond and the payment bond. Such substitute performance does not involve the Award of a new Contract and shall not be subject to the Competitive Procurement provisions of ORS Chapter 279C or these rules.