26.04.080 Life of Permit Limited.

City Code Section

(Replaced by Ordinances 190350 and 191736, effective July 1, 2024.)

  1. A.  Permit applications.
    1. 1.  Initial permit application. A permit application that is inactive for a period of 180 days will be deemed abandoned. If an abandoned permit application is not reactivated within 180 days of abandonment, the permit application will be void. If a permit application is void, a new permit application is required for the subject work.
    2. 2.  Extensions. The Building Official may extend a permit application for up to 180 days, with justifiable cause, as determined in the Building Official’s sole discretion. Extension requests must be in writing and must be received by the Portland Permitting & Development before the scheduled permit abandonment date.
    3. 3.  Reactivations. The Building Official may reactivate a permit application that has been abandoned for less than 180 days, with justifiable cause as determined in the Building Official’s sole discretion. Reactivation requests must be in writing and received by the Portland Permitting & Development within 180 days after permit abandonment date. If no activity occurs within 180 days after a permit application is reactivated, the permit application will be deemed abandoned. A permit application may be reactivated only once.
  2. B.  Issued permits.
    1. 1.  Initial issued permit. If no inspection is approved within 180 days after permit issuance, the permit will expire. If an expired permit is not reactivated within 180 days of expiration, the permit will be void. If a permit is void, a new permit is required for the subject work.
    2. 2.  Extensions. Each time an inspection is approved, the permit will automatically be extended for 180 days. The Building Official may also extend a permit for a period of up to 180 days with justifiable cause, as determined in the Building Official’s sole discretion. Extension requests must be in writing and must be received by the Portland Permitting & Development before the scheduled permit expiration date. If no inspection is approved within the extended time period, the permit will expire. 
    3. 3.  Reactivations. The Building Official may reactivate a permit that has been expired for less than 180 days, provided no changes have been made to the scope of work, and with justifiable cause as determined in the Building Official’s sole discretion. A void permit may be reactivated provided there have been no changes to the scope of work and only the final inspection remains unapproved. Reactivation requests must be in writing and received by the Portland Permitting & Development within 180 days after permit expiration. If no inspection is approved within 180 days of reactivation, the permit will expire. A permit may be reactivated only once.
  3. C.  Fees. When a new permit is required, a new permit application must be submitted and new fees must be paid based on the current adopted Portland Permitting & Development fee schedule. The Portland Permitting & Development will adopt policies for fee refunds or credits of previously submitted permits. Fees for permit extensions and reactivations may also be charged as adopted in the Portland Permitting & Development fee schedule.