South Corbett and Carolina Sewer Repair Project
Sewer and Stormwater
Active
Construction is anticipated to start in early-Summer 2024 and will take up to four months to complete.
Environmental Services is designing a sewer project to replace 250 feet of aging pipes near private properties within the Corbett neighborhood. This project will protect public health and the environment by reducing the possibility of sewage releases to homes, businesses, and streets.
Woods Trunk Sewer Project
Sewer and Stormwater
Active
Construction is expected to begin in February 2027 and take about a year to complete.
Environmental Services is designing a project to repair 1,700 feet of aging, large-diameter brick sewer pipes in South Portland. Having provided over 125 years of service, the pipes require repairs to maintain reliable sewer service and protect public health and the environment.
South Portland-Burlingame Sewer Project
Sewer and Stormwater
Active
Construction began in June 2023 and will take up to a year and a half to complete.
Environmental Services is constructing a project in the South Portland and South Burlingame neighborhoods that will repair approximately 7,108 linear feet of aging public sewer pipes, that are on average 90 years old. This will help protect public health and the Willamette River Watershed.
Carolina Trunk Sewer Project
Sewer and Stormwater
Active
Construction is expected to start in the 2025 and should take about two years to complete.
Environmental Services is designing a project to repair a section of large concrete sewer pipe running from Barbur Boulevard under Interstate 5 to Macadam Avenue. The "Carolina Trunk" sewer pipe was built almost 90 years ago and is in need of repair to prevent sewer and stormwater overflows.