Project Area
The project is located on SE 51st Avenue just north of SE Division Street.
What's Happening Now
Construction is nearing completion and is expected to wrap up by mid‑August. Typical work hours are 7 a.m. to 6 p.m., Monday through Friday. Saturday work may occur if needed.
Week of July 27
- Crews will form and pour concrete for sidewalks and curbs affected during construction.
- Preparation begins for paving SE 51st Ave from south to north.
Week of August 3
- Continued preparation for paving SE 51st Ave (south to north).
- Backfilling curbs and sidewalks.
- Stump grinding and general cleanup.
- Video inspection of the sewer mainline.
- Mid‑week: crews will prepare and pave SE Division St at SE 51st Ave on the south side.
Week of August 10
- Crews will prepare and pave SE Division St at SE 51st Ave on the north side.
- Curb‑to‑curb paving of the construction area along SE 51st Ave (south to north).
What To Expect During Construction
Construction creates noise, vibration, and dust and can disrupt normal neighborhood activity. We want you to be safe around the work site. Please keep children, pets, bikes, cars, and trucks away from the tools, machines, supplies, and construction workers. A city inspector will be on-site during work hours and may be able to assist you with construction concerns. Inspectors typically wear a hard hat and safety vest with "City of Portland" on the back.
Visit portland.gov/bes/constructionimpacts to learn more about what to expect during construction.
Tree Replacement
Two new street trees will be planted in the public right-of-way at no cost to the adjacent property owner. Environmental Services and Urban Forestry are working with the property owner to select the appropriate trees that are approved for locations with high-voltage power lines.
Street Restoration Improvements
As part of this project, Environmental Services will repave SE 51st Avenue curb-to-curb in the area where construction occurs. The existing pavement will be removed and replaced with new asphalt across the full width of the street to restore the roadway after sewer installation.
Construction Methods
Crews will install sewer pipes in SE 51st Avenue using open trench excavation. Learn more at Portland.gov/BES/OpenTrench.
Stay Informed
Environmental Services is committed to keeping residents and businesses informed about project activities and responding promptly to questions and concerns. We encourage you to:
- Provide key details: When leaving a voicemail or sending an email, please include your name, property address, and the project name (SE 51st Ave).
- Sewer emergency or odor concern? Call 503-823-1700 immediately. The City Maintenance hotline is available 24 hours a day, 7 days a week.
Sign Up for Updates
Sign up for periodic email or text message updates for the SE 51st Ave Sewer Extension Project through our free GovDelivery subscription service. These updates are the best way to stay informed about what’s happening and what to expect. You can also sign up for bulletins on other projects and topics.
This project will help protect the health of the Willamette River Watershed.