Miller Creek Fish Passage Project

Sewer and Stormwater
Active
Environmental Services—your sewer and stormwater utility—is designing a project to replace an aging culvert underneath a driveway of Fred’s Marina. The new culvert will improve water quality, remove invasive vegetation, and restore important fish passage and habitat.
The project is currently in the design phase. Construction is anticipated to begin summer 2023 and take six months to complete.
On this Page

Project Area

The project is located at the intersection of the front driveway entrance of Fred’s Marina, 12800 NW Marina Way Portland, OR 97231, and entrance’s culvert.

What's Happening Now

Currently, City engineers and field crews are conducting various investigations to collect information that will help them determine what needs to be repaired or replaced and what construction methods to use for this project.

We want to Hear from You

Environmental Services will inform residents and businesses about project activities and respond to questions and concerns in a timely manner. The following resources will help you stay informed and report concerns:

  • Questions: Call 503-865-4300, please be sure to include your name, property address, and project name (Miller Creek Culvert and Restoration Project) in your voicemail.
  • Sewer Emergency: In the event of a sewer backup or basement flooding, call the Maintenance hotline immediately at 503-823-1700. It is staffed all hours and all days, 24/7.

Sign Up for Project Updates