Miller Creek Fish Passage Improvement Project

Sewer and Stormwater
Active
Environmental Services—your sewer and stormwater utility—is constructing a project to replace an aging culvert underneath a driveway of Fred’s Marina. The new culvert will improve water quality, remove invasive vegetation, and restore important fish passage and habitat.
Construction began in July, 2024 and is expected to take about six months to complete.
On this Page

Project Area

The project is located at  12800 NW Marina Way in Portland.

Miller Creek Fish Passage Improvement Project Map
Project Area Map

What's Happening Now

Work began in July of 2024. Construction hours for this project are expected to be 7 a.m. to 6 p.m. Monday through Friday, with some work possible on Saturdays if needed.

All work is weather dependent, and the schedule below is subject to change. Please visit the construction methods webpage to learn more about types of construction methods being used.

Week of September 9

The following work is expected to occur:

  • Install temporary access bridge and road.
  • Install water management barriers.

Week of September 16

The following work is expected to occur:

  • Remove and relocate aquatic species in the work area.
  • Relocate utilities.
  • Begin removing old culvert.

Week of September 23

The following work is expected to occur:

  • Begin installing new culvert.

What to Expect During Construction

We want you to be safe around the work site. Please keep children, pets, bikes, cars, and trucks away from the tools, machines, supplies, and construction workers. A city inspector will be on-site during work hours and may be able to assist you with construction concerns. Inspectors typically wear a hard hat and safety vest with “City of Portland” on the back. Learn more about what to expect during construction online at Construction Impacts.

We want to Hear from You

Environmental Services will inform residents and businesses about project activities and respond to questions and concerns in a timely manner. The following resources will help you stay informed and report concerns:

  • Project Updates: To receive email or text message updates for this project, sign up now at Sign Up for BES Project Updates. Updates provided through our free GovDelivery subscription service are the best way to stay informed about what’s happening and what to expect. You can also sign up for bulletins on other projects and topics 
  • Questions: Contact Aaron Abrams at Aaron.Abrams@portlandoregon.gov or call 503-823-2827.  
  • Sewer Emergency: Call 503-823-1700 immediately. The City Maintenance hotline is staffed all hours, all days (24/7).  