The Lombard Pump Station, located at 12902 N Lombard Street, was built in 1983. It pumps sewage and stormwater from North Portland to the Columbia Boulevard Wastewater Plant. Its service area includes 3,800 acres in north Portland which primarily consists of commercial and industrial users.
The pump station is being upgraded to meet current codes, regulations, and pump station design guidelines. Improvements to the pump station will include ground improvements to increase resiliency, upgrades to equipment, and building a permanent on-site generator to provide standby backup power.
Project Area
The project area includes work on the pump station off N Columbia Boulevard between Rivergate Boulevard and Lombard Street, and the force main along N Columbia Boulevard and into Chimney and Pier parks.
Text description of the Lombard Pump Station and Force Main Project Map
What's Happening Now
Crews work Monday through Friday, 7 a.m. to 6 p.m., weather permitting. Please note that the schedule may change due to weather, supply deliveries, or equipment availability.
November and December 2026
- Work continues at the Lombard Pump Station site near the Columbia Slough.
- There may be intermittent work in Pier Park.
What to Expect During Construction
You can expect the following activities and impacts during construction. This area is not as impacted due to limited residential properties:
- Noise, Vibration, and Dust: Construction creates noise, vibration, and dust, and disrupts normal neighborhood activity.
- Equipment Storage: Equipment and materials may be stored on streets overnight.
- No Parking: Little or no on‐street parking will be allowed in and near work zones, especially during work hours. On days when crews will be working in front of your house or nearby, please plan ahead. If you park your vehicle on the street, plan to move it off the street by 7 a.m. and return it at 6 p.m.
- Traffic Delays: Expect traffic delays in and near the work area. The contractor will develop detailed traffic control plans for each location.
- Pedestrian Access: If temporary crosswalk and sidewalk closures are necessary, signage will indicate the alternate way for pedestrians to proceed.
- Services Maintained: Sewer, water, and other utilities are expected to remain in service during construction.
- Garbage Pickup: Access to garbage and recycling bins for haulers will always be maintained.
- Schedule Changes and Inactivity: Construction schedules can change due to a variety of factors, including conditions underground, weather, traffic impacts, subcontractor schedules, and availability of materials. These same variables may cause periods of inactivity during construction phases.
Stay Informed!
Environmental Services will work closely with nearby residents, businesses, and property owners throughout the project. Our outreach team is available to listen to concerns and respond to questions.
- Visit this webpage for ongoing updates.
- For questions or comments, contact Debbie Caselton by email or phone at 503-823-2831.
- Please reach out if you have concerns related to business operations, special events, access, or other site-specific issues. When contacting us, include your name, property address, business name (if applicable), and the project name Lombard Pump Station and Force Main in your message or email subject line.
- If your basement sewer backs up or your property or street floods, report it immediately to the City's Maintenance Operations hotline at 503-823-1700 (available 24/7).
Sign Up for Updates
Sign up for periodic email or text message updates for the Lombard Pump Station and Force Main Upgrade through our free GovDelivery subscription service. These updates are the best way to stay informed about what’s happening and what to expect. You can also sign up for bulletins on other projects and topics.
This project will help protect the health of the Columbia Slough Watershed.