BDS has adopted an Interim Demolition Administrative Rule, effective February 10, 2020, that revises the inspection requirements for demolitions of structures used for residential purposes with four or fewer dwelling units and any detached accessory structures with a floor area over 200 square feet.
Published
Updated
In this article
CUSTOMER & COMMUNITY NOTIFICATION

SERVICE UPDATE
February 10, 2020

(Update) BDS Adopts Interim Residential Demolition Administrative Rule

New information about residential demolition inspection requirements is now available. There is a requirements handout, live-video customer instructions, demolition ordinance, and the interim administrative rule. To view the full page, click here: www.portlandoregon.gov/bds/80378


CUSTOMER & COMMUNITY NOTIFICATION

SERVICE UPDATE
January 24, 2020

BDS Adopts Interim Residential Demolition Administrative Rule

The Bureau of Development Services (BDS) has adopted an Interim Residential Demolition Administrative Rule, effective February 10, 2020, that revises the inspection requirements for demolitions of residential structures with four or fewer dwelling units and any detached accessory structures with a floor area more than 200 square feet on the same site. 

The Interim Rule requires the Demolition Manager or Lead-Based Paint Certified Person to meet with the inspector at the #200 inspection, in addition to the other requirements. The Rule also requires two #205 inspections that must be requested and scheduled through the City’s Interactive Voice Response (IVR) system.  The first of these inspections now requires that the Demolition Manager or Lead-Based Paint Certified Person is on-site during the inspection and that the exterior painted surfaces have been removed. The second #205 inspection must be scheduled so that the inspector is on-site when mechanical demolition begins in order to verify the effectiveness of the dust suppression wetting system and the wind speed. The second #205 inspection may be conducted via a live-streaming inspection using live video streaming technology pre-approved by BDS. There are no changes to the #210 inspection.  

The Interim Rule will be effective for 180 days from February 10, 2020 or until the permanent rule is adopted.


The City of Portland is committed to providing meaningful access. For accommodations, modifications, translation, interpretation or other services, please call 503-823-7300, the TTY at 503-823-6868 or the Oregon Relay Service: 711. Traducción e interpretación | Chuyển Ngữ hoặc Phiên Dịch
翻译或传译 | Письменныйили устный перевод | 翻訳または通訳 | Traducere sau Interpretare
번역 및 통역 | Письмовий або усний переклад | Turjumida ama Fasiraadda
Image removed.  | Image removed.

Contact

General Inquiries

Development Services
phone number503-823-7300Our front desk team will be available to answer Monday through Friday from 8 a.m. to 5 p.m. Please leave a message if you call outside of those hours.
Oregon Relay Service711Oregon Relay Service